Oil & Gas Glossary 1.0
OIL & GAS TECHNICAL TERMS GLOSSARY
If you are looking for a definition of any technical terms in oil & gas field, then this site is yours.
Until now, we've collected around 2000 technical terms, but if this still not enough, and you've found any term that is not in our database, please contact us, and we will happily find it for you, or you can just check it again later, because every unsuccessful search will be recorded by our system for later update.
Thanks and happy searching ^^.
Search Result for Conventional Completion
miniaturized completion
A well completion in which the production casing is less than 4.5 inches in diameter. Compare conventional completion.
conventional completion
A method for completing a well in which tubing is set inside 4-1/2-inch or larger casing.
slim-hole drilling
Drilling in which the size of the hole is smaller than the conventional hole diameter for a given depth. This decrease in hole size enables the operator to run smaller casing, thereby lessening the cost of completion. See miniaturized completion.
open-hole completion
A method of preparing a well for production in which no production casing or liner is set opposite the producing formation. Reservoir fluids flow unrestricted into the open wellbore. An open-hole completion has limited use in rather special situations. Also called a barefoot completion.
recompletion
After the initial completion of a well, the action and techniques of reentering the well and redoing or repairing the original completion to restore the well's productivity.
barefoot completion
See open-hole completion
tubingless completion
A method of producing a well in which only production casing is set through the pay zone, with no tubing or inner production string used to bring formation fluids to the surface. This type of completion has its best application in low-pressure, dry-gas reservoirs.
turnkey contract
A drilling contract that calls for the payment of a stipulated amount to the drilling contractor on completion of the well. In a turnkey contract, the contractor furnishes all material and labor and controls the entire drilling operation, independent of operator supervision. A turnkey contract does not, as a rule, include the completion of a well as a producer.
conventional mud
A drilling fluid containing essentially clay and water; no special or expensive chemicals or conditioners are added.
dual completion
A single well that produces from two separate formation at the same time. Production from each zone is segregated by running two tubing strings with packers inside the single string of production casing, or by running one tubing string with a packer through one zone while the other is produced through the annulus. In a miniaturized dual completion, two separate 4 1/2-inch or smaller casing strings are run and cemented in the same wellbore.
dovetail
A cutout section in a cone enabling positive slip movement without the aid of conventional slip return springs
button slip
A slip employing tungsten-carbide "buttons" in lieu of conventional wicker-type teeth to set tools in very hard casing.
completion
Refers to the installation of permanent equipment for the production of oil or gas.
multiple completion well
A well equipped to produce oil and/or gas separately from more than one reservoir.
stack a rig
To store a drilling rig on completion of a job when the rig is to be withdrawn from operation for a time.
complete a well
To finish work on a well and bring it to productive status. See well completion.
oil-in-water emulsion mud
Any conventional or special water-base mud to which oil has been added. The oil becomes the dispersed phase and may be emulsified into the mud either mechanically or chemically. Also called oil-emulsion mud.
dry hole
An exploratory or development well found to be incapable of producing either oil or gas in sufficient quantities to justify completion as an oil or gas well.
field facility
An installation designed for one or more specific and limited extraction units, scrubbers, absorbers, drip points, conventional single or multiple stage separation units, LTX low temperature separators, and other types of separation and recovery equipment.
concentric tubing workover
A workover performed with a small-diameter tubing work string inside the normal tubing. Equipment needed is essentially the same as that for a conventional workover except that it is smaller and lighter.
well completion
1. the activities and methods of preparing a well for the production of oil and gas or for other purposes, such as injection; the method by which one or more flow paths for hydrocarbons are established between the reservoir and the surface.
well completion
2. the system of tubulars, packers, and other tools installed beneath the wellhead in the production casing; that is, the tool assembly that provides the hydrocarbon flow path or paths.
production test
A test of the well's producing potential usually done during the initial completion phase
waiting on cement (WOC)
Pertaining to the time when drilling or completion operations are suspended so that the cement in a well can harden sufficiently.
skin
1. the area of the formation that is damaged because of the invasion of foreign substances into the exposed section of the formation adjacent to the wellbore during drilling and completion.
breaking down
Unscrewing the drill stem into single joints and placing them on the pipe rack. The operation takes place on completion of the well, or in changing from one size of pipe to another.
core
N: a cylindrical sample taken from a formation for geological analysis. Usually a conventional core barrel is substituted for the bit and procures a sample as it penetrates the formation. v: to obtain a formation sample for analysis.
completion fluid
Low-solids fluid or drilling mud used when a well is being completed. it is selected not only for its ability to control formation pressure, but also for the properties that minimize formation damage.
dilatant fluid
A dilatant, or inverted plastic, fluid is usually made up of a high concentration of well-dispersed solids that exhibits a nonlinear consistency curve passing through the origin. The apparent viscosity increases instantaneously with increasing rate of share. The yield point, as determined by conventional calculations from the direct-indicating viscometer readings, is negative; however, the true yield point is zero.
gravel-pack packer
A packer used for the well completion method of gravel packing.
conventional gravel pack
A type of gravel pack where the wells production packer is removed and a service packer is run in with the gravel pack assembly. After packing, the service tool is retrieved and the production packer rerun.
gravel packing
A method of well completion in which a slotted or perforated liner, often wire-wrapped, is placed in the well and surrounded by gravel. If open hole, the well is sometimes enlarged by underreaming at the point where the gravel is packed. The mass of gravel excludes sand from the wellbore but allows continued production.
formation testing
The gathering of pressure data and fluid samples from a formation to determine its production potential before choosing a completion method. Testing tools include formation testers and drill stem test tools.
workover fluid
Any type of fluid used in the workover operation of a well. See completion fluid.
drill stem test (DST)
The conventional method of formation testing. The basic drill stem test tool consists of a packer or packers, valve or ports that may be opened and closed from the surface, and two or more pressure-recording devices. The tool is lowered on the drill string to the zone to be tested. The packer or packers are set to isolate the zone from the drilling fluid column. The valves or ports are then opened to allow for formation flow while the recorders chart static pressures. A sampling chamber traps dean formation fluids at the end of the test. Analysis of the pressure charts is an important part of formation testing.
blowout preventer
One of several valves installed at the wellhead to prevent the escape of pressure either in the annular space between the casing and drill pipe or in open hole (i.e., hole with no drill pipe) during drilling completion operations. Blowout preventers on land rigs are located beneath the rig at the land's surface; on jackup or platform rigs, at the water's surface; and on floating offshore rigs, on the seafloor.
multiple completion
An arrangement for producing a well in which one wellbore penetrates two or more petroleum-bearing formations. In one type, multiple tubing strings are suspended side by side in the production casing string, each a different length and each packed to prevent the commingling of different reservoir fluids. Each reservoir is then produced through its own tubing string. Alternatively, a small-diameter production casing string may be provided for each reservoir, as in multiple miniaturized or multiple tubingless completions.